Recycling Depot Expansion

See the 2007 component for project history.

The 2008 Capital Budget includes the remaining site improvements to complete this project. This involves full road base reconstruction with the installation of concrete curb and gutter to control traffic and drainage. A second entrance will be constructed to provide better traffic flow on the site.

**Expect major delays during construction.

Contractor:

Jo's Concrete Services Ltd. was awarded the contract for the concrete work.
Border Paving was awarded the contract for the base gravel installation and paving.

Budget:

This component of the project is estimated to cost $100,000.

Schedule:

Concrete curb, gutter and entrances have been completed. Paving is scheduled for August.

Photos:

Recycling Depot Expansion Recycling Depot Expansion
February 1 - Completed building. June 6 - Forms setup in preparation for concrete installation.
Recycling Depot Expansion Recycling Depot Expansion
July 25 - Excavation of the approach. August 5 - Completed concrete entrance.
Recycling Depot Expansion  
August 5 - Completed concrete entrance.  
  Home  Search  Index  Feedback  Privacy and Condition of Use StatementWe welcome your feedback
Updated August 5, 2008

Copyright © 2007 The City of Camrose
TM "The Rose City" and design is a Trademark the property of The City of Camrose

Copyright and Disclaimer | Conditions of Use and Privacy Statement