Welcome
Visitors
Community
City of Camrose
Admin
Leisure
Engineering
Protective

City Engineer | Building Inspection | Electrical Inspection | Engineering Services | Planning | Plumbing, Gas, Heating Inspection |Public Works

2008 Construction Program | 2007 Construction Program | 2006 Construction Program


Water Treatment Plant Upgrade
Granular Activated Carbon (GAC) Contact Facility

Last Modified Apr 4, 08

Partially Funded by:

Alberta Infrastructure and Transportation logo

Project Profile:

GAC Facility Aerial Photo

This project will involve the construction of an auxiliary Granular Activated Carbon (GAC) contact facility at the Camrose Water Treatment Plant (WTP). The GAC facility will provide an additional treatment step after the existing water treatment plant process to remove additional organic molecules from the water. The end result of this construction will include water with an improved taste and reduced odor, and allow for a higher level of disinfection using lower levels of chlorine.

GAC Process Layout
















The GAC contact facility will consist of a new structure, approximately 34 metres (m) long by 18 m wide, which will be located on the existing City lands immediately NW of the existing WTP. The structure will house:

  • 6 pre-purchased Calgon Carbon Modular Model 12 GAC contact chambers; the tanks will be approx. 5.2 m tall and 3.6 m in diameter, and will each have a design flow capacity of approx. 27.8 litres per second (L/s), when run as stand alone units; the piping within the GAC facility will be arranged to allow for flexibility of running the tanks in series or parallel, depending on the specific daily needs of the City; the current arrangement of 6 GAC contact tanks will allow for the treatment of up to 15 million litres of water per day (ML/d).
  • 2 future GAC contact tanks, which can be added once water demands within the City have increased to the point at which these units are needed
  • 24.45 m3 of carbon to fill each tank, as well as storage areas to handle bulk unused and waste carbon.
  • 2 pre-purchased Trojan Technologies UVSwift 4L24 Ultraviolet (UV) disinfection reactors; the reactors will each be approximately 0.6 m in diameter, will contain four 9.7 kW lamps, will be located in-line with the existing water flow through the GAC facility, and have been sized for current and future expected flow rates.
  • All necessary piping, valves, instrumentation controls, etc., to ensures the flexibility and efficiency of the facility.
GAC Site Layout GAC Facility with Existing WTP

The architectural façade of the building has been designed to be compatible with the existing facilities at the WTP, and the area around the new GAC facility will be properly landscaped with grass & trees.

Engineering:

The design and site supervision of this project will be conducted by the City Engineering Department and ISL Engineering and Land Services.

Contractor:

Maple Reinders Inc., of Edmonton, has been awarded the contract for the construction of this facility. As part of their contract with the City, Maple Reinders will install the pre-purchased GAC and UV equipment into the new facility.

Budget and Funding:

The total project budget is $6,789,000, broken down as follows:

  • Pre-purchased GAC & UV equipment – $1,215,000
  • Additional materials & labour (Maple Reinders contract) – $4,196,000
  • Additional equipment (not included in Maple Reinders contract) – $108,000
  • Engineering – $890,000
  • Contingency – $380,000

This project will be funded as follows:

  • Alberta Municipal Water/Wastewater Partnership – $2,000,000
  • Water System Reserves – $1,100,000
  • Debenture Borrowing (Bylaw # 2499/06, approved by Council on July 10/06) – $2,500,000
  • 2006 Water Capital (carry-over from approved 2006 budget) – $400,000
  • 2007 Water Capital – $300,000
  • 2008 Water Capital – $489,000

Schedule:

This project is expected to be substantially complete by summer 2008.

Underground concrete tanks are complete. The building floor was constructed in mid-September, and the structural steel building was erected in late November.

Pre-purchase GAC equipment was delivered and moved into the GAC building in mid-December 2007. GAC piping installation should be completed by mid-April 2008.

Remaining work is scheduled for the summer of 2008.

Photos:

August 8 - Foundation finalization. August 8 - Concrete form in place for preparation of additional wall pouring.
August 9 - Newly installed piping (400mm and 500mm) will connect the GAC Facility to the Water Treatment Plant. August 9 - Concrete truck pours one on the water storage well walls.
 
November 14 - Floor slab pouring has been completed in preparation of the installation of structural steel building.  

Public Notice:

For more information contact the Engineering Department at 672-4428.

  Home  Search  Index  Feedback  Privacy and Condition of Use StatementWe welcome your feedback
Updated April 4, 2008

Copyright © 2007 The City of Camrose
TM "The Rose City" and design is a Trademark the property of The City of Camrose

Copyright and Disclaimer | Conditions of Use and Privacy Statement