Rosebud Area
|
| Total Project Cost | $1,500,000 |
| City of Camrose Contribution | $1,056,000 |
| Local Improvement | $444,000 |
Schedule:
Underground work was completed by early July.
Excavation of the roads is complete.
Concrete curb, gutter and sidewalks are 80% complete. Remaining concrete work is scheduled for May 2007.
Paving will immediately follow the completion of the concrete work.
Photos:
![]() | ![]() |
| May 23 - Installation of the 750mm storm main on 52B Avenue between 43 and 44 Street. | May 30 - Installation of the 750mm storm main on 52B Avenue between 43 and 44 Street. |
![]() | ![]() |
| June 12 - Backfilling with gravel for under the pipe stability to prevent "sagging". | June 12 - Fitting the new pvc sewer main to match the old clay main. |
![]() | ![]() |
| June 12 - Installation of the 1200mm barrels to bring the top of the man hole up to road grade. | July 13 - Excavation for curb and gutter installation. |
![]() | ![]() |
| August 18 - Completed concrete curb and gutter. | August 18 - Forming and pouring of concrete sidewalks. |
![]() | ![]() |
| September 30 - Excavating existing curb and gutter. | September 30 - Completed concrete sidewalk and excavated curb and gutter. |
![]() | ![]() |
| October 23 - Installation of concrete curb and gutter. | October 23 - Completed concrete curb and gutter. |
Public Notice:
For more information contact the Engineering Department at 672-4428.