Valleyview Residential Lot Development
Phase 1 and 2

Project Background:

The Vallyview development is a multi staged residential subdivision development being constructed in the south of Camrose Drive and Parkview Drive.

For more information on lot availability and prices, please contact Dennis Twomey at City Hall, 672-4426 or see our online brochure.


Project Profile:

In the fall of 2003 the installation of deep underground utilities was initiated (2004 component). Deep utilities are installed at least one year in advance of any surface improvements such as paving and sidewalks. The majority of trench settlement occurs within the first year of installation. By delaying surface improvements we minimize concrete cracking and "dips" in road surface resulting in a higher quality product for the property purchaser.

The 2005 Phase 1 component of this project involves surface improvements and includes curb, gutter, sidewalk and paving. Shallow utilities and street lights will follow.

The 2005 Phase 2 component of this project involves surface improvements and includes curb, gutter and paving. Shallow utilties and street lights will follow in 2006.


Valleyview Residential Lot Development

Engineering:

The design and site supervision of this project is being conducted by the City Engineering Department and Bel-MK Engineering Ltd.

Contractors:

Border Paving has been awarded the Phase 1 and 2 surface work contracts. Joe's Concrete has been awarded the contract for the sidewalks in Phase 1 and Proform Concrete has been awarded the contract for the curb and gutter in Phase 1 and 2.

Budget and Funding:

The budget to complete Phase 1 of development is $800,000 with funding from the City Land Fund Reserve / Lot sales.

The budget to complete Phase 2 of development is $1,500,000 with funding from the City Land Fund Reserve / Lot sales.

Schedule:

  • Lots were available as of August 1st. For more information on lot availability and prices, please contact Dennis Twomey at City Hall, 672-4426
  • Paving and concrete work for Phase 1 was completed by the end of August.
  • Paving and concrete curb and gutter work for Phase 2 was completed by mid October.
  • Shallow utilities for Phase 1 were completed by the end of September.
  • Shallow utilities for Phase 2 are scheduled for the spring of 2006.
  • Installation of pedestrian activated traffic control devices completed by the end of December.

Photos:

Curb and gutter installation complete in Phase 1.Storm retention pond.
Completed trails abutting pond in Phase 1.Road base construction on Valleyview Drive.
Cement stabalization of road base.Prime oil coat on gravel base.
Prime oil coat on gravel base.Placing of bottom lift of asphalt.
Compaction of asphalt.Road base preparation just prior to curb installation.
Concrete forms being setup.Complete sidewalk in forms.
Paving completed on 28 Avenue.Concrete roundabout completed.
Completed trails abutting Valley.Paving and concrete work completed.
Installation of traffic control devices at the
Camrose Drive / Parkview Drive intersection.
Completed concrete curb, gutter and paving in Phase 2.
Valleyview Phase 1 lot development in progress.

Public Notice:

For More Information Contact the Engineering Department at 672-4428.

  Home  Search  Index  Feedback  Privacy and Condition of Use StatementWe welcome your feedback
Updated April 21, 2006