Cell Development Last Modified November 17, 2005 Project Profile: Based on the current disposal rates, a new landfill cell will be required by the end of 2005. The construction falls in line with the design cycle of 1 1/2 to 2 years per cell. ![]() Engineering: The design and site supervision of this project will be conducted by the City Engineering Department and GPEC Consulting. Contractor: Wally's Backhoe Services Ltd. Budget and Funding: The total 2005 budget for the landfill cell development is $120,000. Schedule: This project was completed by the beginning of November. Photos:
Public Notice: For More Information Contact the Engineering Department at 672-4428. |