Project Profile:

The 41 Street Industrial lot development will be a multi staged development constructed in the heart of the Camrose industrial area.

With lot sales remaining strong for industrial lots, the City is proceeding with the first stage of this subdivision providing 1 acre lots abutting the existing 41st Street between 42-44 Avenue.

For more information on lot availability and prices, please contact Dennis Twomey at City Hall, 672-4426.

In conjunction with this lot development, the City plans to complete the "CN Storm Retention Pond". Sanitary sewer mains were relocated in 2004 in anticipation of the final excavations of the storm pond. Additional storm sewer piping will be required to complete the construction of the pond this year.

The City is also proposing to construct a "Snow Disposal" facility in this same area. Associated Engineering of Edmonton will be undertaking the design and citing of the facility with the intention of construction coinciding with the pond installation.

Engineering:

The design and site supervision of this project will be conducted by the City Engineering Department and Associated Engineering.

Contractor:

Kran Construction Ltd. will undertake the Earthwork / Pond Construction.

Budget and Funding:

The budget to complete these projects is $1,300,000.00 with funding from City Land Fund Reserve / Off Site Levy's.

Schedule:

Construction of the CN Storm Retention Pond was completed by late November.
Construction of the Snow Disposal Facility was completed by the end of November.
Remaining work has been postponed until 2006.
Industrial lot development has been postponed until 2006.

Photos:

Existing storm pond.Stripping topsoil in preparation for clay dump.
Topsoil stripping complete.Storm pond construction has begun.
Storm pond grading in progress.Storm pond grading in progress.
Section of completed storm pond.Completed storm retention pond.
Snow Disposal Facility under construction.

Public Notice:

For More Information Contact the Engineering Department at 672-4428.

  Home  Search  Index  Feedback  Privacy and Condition of Use StatementWe welcome your feedback
Updated December 16, 2005

Copyright © 2007 The City of Camrose
TM "The Rose City" and design is a Trademark the property of The City of Camrose

Copyright and Disclaimer | Conditions of Use and Privacy Statement