Parkview Drive Overlay

39 Avenue to 43 Avenue

Partially Funded by:

Alberta Transportation logo

Project Profile:

Parkview Drive was constructed in the late 80's and the asphalt surface is now showing signs of distress.

The City proposes to construct an asphalt overlay on top of the existing road service, which should extend the life of the existing road structure another ten to twenty years. An asphalt planer will be used to remove asphalt along the gutter line so that the new pavement matches the existing gutter.

New permanent lane markings will be applied, once the project is complete.

Parkview Drive Overlay Project Layout

Engineering:

The design and site supervision of this project will be conducted by the City Engineering Department.

Contractor:

Border Paving Ltd. and Lafrentz Road Services Ltd. were awarded the contracts for this project.

Budget and Funding:

Total Project Cost$100,000
City of Camrose Contribution$40,000
Provincial Transportation Grant$60,000

Schedule:

Parkview Drive OverlayParkview Drive Overlay
Asphalt being delivered to paver.Tack coat oil.
Parkview Drive OverlayParkview Drive Overlay
Outside lanes paved first to accomodate traffic flow.Paving completed. Permanent markings installed immediately after.

Public Notice:

For More Information Contact the Engineering Department at 672-4428.

  Home  Search  Index  Feedback  Privacy and Condition of Use StatementWe welcome your feedback
Updated February 4, 2005