Century Meadows

56 Lot Development

Project Background:

Century Meadows is a multi staged residential subdivision development located in the southwest corner of Camrose. 211 of the 267 lots have been completely serviced. The majority of these lots have now been sold. In 2003, the final phase of this development will be constructed, servicing the remaining 56 lots. Construction is expected to be completed with the lots available for sale by the end of July 2003.

This phase will complete the development of the Century Meadows area.

For more information on lot availability and prices, please contact Dennis Twomey at City Hall, 672-4426.

Project Profile:

In the spring 2001 the installation of underground utilities to complete the deep servicing was completed. Deep utilities are installed at least one year in advance of any surface improvements such as paving and sidewalks. The majority of trench settlement occurs within the first year of installation. By delaying surface improvements we minimize concrete cracking and "dips" in road surface resulting in a higher quality product for the property purchaser.

The construction of surface improvements (paving & sidewalks, shallow utilities, street lighting etc.) this spring will complete the 30 & 31 Avenue loops in the south west corner of the development (see map). The boulevards in the area will be topsoiled with tree planting in October.

2002 Project Description
2001 Project Description

Century Meadows Phase V Project Layout

Engineering:

The design and site supervision of this project will be conducted by the City Engineering Department.

Contractor:

Border Paving Ltd., Branco Concrete, D & H Concrete Services Ltd. and McGregor Construction 2000 Ltd. were awarded the contracts for this project.

Budget and Funding:

The budget to complete the surface component of the development is $750,000.00 with funding from City Land Fund Reserve which is supported by lot sales revenue.

Schedule:

Miscellaneous concrete work remains to finish the project and is scheduled for 2004.

Photos:

Century Meadows Phase V ConstructionCentury Meadows Phase V Construction
Sanitary sewer, storm sewer and water mains were installed in 2001.Soil quantities balanced in order to prepare the road for gravel base and subsequent paving.
Century Meadows Phase V ConstructionCentury Meadows Phase V Construction
Border Paving installing geotextile fabric in preparation for concrete and paving.Border Paving is hauling in crushed gravel in preparation for concrete and paving.
Century Meadows Phase V ConstructionCentury Meadows Phase V Construction
Curb and gutter machine extrudes the concrete into place.Curing solution is sprayed on fresh concrete.
Century Meadows Phase V ConstructionCentury Meadows Phase V Construction
Sidewalk forms ready for concrete.Concrete being poured and levelled off.
Century Meadows Phase V ConstructionCentury Meadows Phase V Construction
Concrete finisher at work.Broom finished sidewalk.
Century Meadows Phase V ConstructionCentury Meadows Phase V Construction
Bottom lift paving completed.Trenches being dug for power.
Century Meadows Phase V ConstructionCentury Meadows Phase V Construction
Power lines being laid out in trenches.Transformer installation.

Gas lines installed by mid October.

Public Notice:

For More Information Contact the Engineering Department at 672-4428.

  Home  Search  Index  Feedback  Privacy and Condition of Use StatementWe welcome your feedback
Updated February 4, 2005

Copyright © 2007 The City of Camrose
TM "The Rose City" and design is a Trademark the property of The City of Camrose

Copyright and Disclaimer | Conditions of Use and Privacy Statement