Project Profile:

Businesses along 47th Avenue encouraged City Council to initiate a local improvement, to undertake the asphalt paving of the existing gravel road abutting the properties.

The project involves the placement of approximately 150mm of road crush gravel and 125mm of asphalt paving. Improvements to the ditch grading will also be included.

47 Avenue Industrial Park Layout

Engineering:

The design and site supervision of this project will be conducted by the City Engineering Department.

Contractor:

Border Paving was awarded the contract for this project in 2003.

Budget and Funding:

The estimated cost as reflected in the local improvement bylaw for the project was $228,000 of which approximately $34,000 was funded by the City of Camrose.

Schedule:

  • A local improvement bylaw was iniciated by the City of Camrose in August 2003.
  • The local improvement bylaw was passed in September 2003.
  • Design completed by mid October.
  • Construction postponed until the spring of 2004.

Public Notice:

For More Information Contact the Engineering Department at 672-4428.

  Home  Search  Index  Feedback  Privacy and Condition of Use StatementWe welcome your feedback
Updated February 4, 2005

Copyright © 2007 The City of Camrose
TM "The Rose City" and design is a Trademark the property of The City of Camrose

Copyright and Disclaimer | Conditions of Use and Privacy Statement