Water and Sewer Service Replacement

54 Street (53 - 54 Avenue)

Partially Funded by:

Alberta Transportation logo

Project Profile:

This project is a continuation of the work undertaken last fall on the block south. The City began a program of replacing water and sewer services in problem areas.  In those cases the mains are in good condition, however the services to property require upgrading or replacement due to a variety of problems. This program has been in place for several years.

 

City Public Works has determined that 54th Street from 52nd to 54th Avenue is one of the highest priority locations based on the poor condition of the sewer service lines. The City will upgrade the water service at the same time as both lines run in a common service trench.

 

A temporary water service will be installed to provide water to anyone affected by the water and sewer service replacement.

 

54th Street will be closed to vehicles for the duration of the construction, approximately 3 weeks. A notice will be given to any properties affected by the construction. Adjacent roadways and lanes will provide an alternative access to homes in the area.

  

  

Engineering

 

Design and site supervision of this project will be conducted by the City Engineering Department.

 

 

Contractor

 

The contractor for this project was selected through a public tender process in 2001. Central Oilfield Services Inc. is the contractor.

 

 

Budget and Funding

 

The total project budget is $105,000 with funding from City water rates and Infrastructure Grant.

 

Total Project Cost

$105,000.00

City of Camrose Contribution

$  55,000.00

Provincial Grants 

$  50,000.00

 

 

Schedule

 

Excavation for the water and sewer service connection has begun.

  • Water and Sewer service connection is complete. Border Paving has completed rebuilding the gravel base. Paving and concrete replacement is scheduled for 2003.

 

 

Public Notice

 

For More Information Contact the Engineering Department at 672-4428.

  Home  Search  Index  Feedback  Privacy and Condition of Use StatementWe welcome your feedback
Updated February 4, 2005

Copyright © 2007 The City of Camrose
TM "The Rose City" and design is a Trademark the property of The City of Camrose

Copyright and Disclaimer | Conditions of Use and Privacy Statement