In 1999 the Camrose 43 Avenue Trunk Sewer main was constructed along 43rd
Avenue from Kin Park to 67 Street. The construction was
restricted for the most part to one half of the roadway width. At the
end of the season, an asphalt patch was placed over the trench.
43rd Avenue was originally constructed between 1972
and 1978, so the asphalt is between 22 and 28 years old. Asphalt in a
residential road is designed to last between 15 and 20 years before requiring
an overlay. The existing asphalt on 43rd Avenue was
experiencing cracking and there were many settlements.
In 2000 it was planned to overlay the entire road width, for
the length of 43rd Avenue in the area disturbed by
construction. The project also included an overlay on 63rd
Street from 43rd Avenue to 44th Avenue, 66th
Street from 42nd Avenue to 43rd Avenue, and 42nd
Avenue from 66th Street to 67th Street. This will bring
these roads back to "new" condition for the entire length, improve
drainage (because the road center, or crown, will be raised), and eliminate
the settlements and cracking which currently exist.
Spot repairs have been made to any curbs or sidewalks which
had settlements which either made them unsafe, or which caused drainage
problems. Prior to placing the asphalt overlay, the asphalt will then be
planned next to the curb so that the new asphalt will match the gutter.
A 40 mm asphalt layer will be applied to the entire width.
In areas where the sidewalks are cracked, residents were given
the option to have the sidewalk replaced, but had to contribute 1/3 of the
replacement cost.
An Open house was hosted April 19th, 2000, for the
residents and property owners along 43rd Avenue to discuss the
project and get input about the design and any problems that they are having
with the existing street such as surface drainage. The project schedule,
and access issues during construction were also be discussed.

Budget and Funding
The total budget for this project is $240,000.00.
The paving overlay project is funded 25% by area property
owners, and 75% by the City at large.
The city policy for local road overlays is that 50% of the
project cost are charged to adjacent property owners via a 'local improvement
by-law'. Because this project was triggered by the 1999 sanitary trunk
project, and normally would not have been considered until the road had
degraded significantly more than it has, Council agreed that property owners
should be charged 25% instead of the normal 50%. As the road is over 20
years old and has significant cracking and settlements, City Council did not
feel it would be fair to overlay the road without charging the property owners
a portion of the costs.
Because this project is funded by a local improvement by-law,
the affected property owners had the right to stop the project if they did not
feel it is warranted, by submitting a valid petition.
No petition was received, so Council approved the Local
Improvement By-Law in May 2000.
Property owners, they have the option of either paying their
share in a lump sum, or applying the cost to their taxes over a ten year
period.
-
Local Improvement By-Law - Given First Reading March 27th,
2000.
-
Open House to explain funding and options to local property
owners - April 19th, 2000
-
Local Improvement By-Law - Final Reading - May, 2000
-
Miscellaneous Concrete Repairs: - June 2000
-
66th Street was paved in August 2000.
-
43rd Avenue paving completed by August 2002.
There have been more settlements than expected on 43rd
Avenue following the sanitary sewer construction in 1999. These
settlements have been patched as they occur, but we are concerned that they may
continue into 2001. As we do not want to have settlements on the "New
Road" after the asphalt overlay, we have delayed the overlay of 43rd
Avenue to the Summer of 2002. The roadway will be re-assessed at that
time.
With the road construction delayed, the local improvement levy
will not be applied until the year following final construction (likely
Construction - 2002, levy applied - 2002). The Municipal Government Act
allows the City three years to complete a project after a local improvement
by-law is passed.
 |  |
| Milling and pre-leveling (the filling in of any uneven areas in the road with hot mix asphalt) are complete. | Paving was completed by June 11th, 2002. |
Public Notice
For More Information Contact the Engineering Department at 672-4428.