 |
City Engineer | Building Inspection | Electrical Inspection | Engineering Services | Planning | Plumbing, Gas, Heating Inspection |Public Works
2008 Construction Program
| 2007 Construction Program
| 2006 Construction Program
Camrose Drive
Bridge Deck Resurfacing
Partially Funded by:

Project Profile
This project
includes replacement of the asphalt and waterproofing membrane on the Camrose
Drive Bridge.
Description
Bridge
structures are designed to expand and contract with temperature, and to flex
under traffic loading. This continual flexing results in failures in the
surface sooner than would be expected on a normal section of roadway.
Bridge decks can typically be expected to last ten years before requiring
some form of resurfacing.
The Camrose Drive Bridge was constructed in
1987. Some problems with the road surface were noted in 1997. Temporary repairs were
made in 1998 with the intention of extending the surface life for a few more
years. We do not believe we can extend the life of the pavement any further,
without compromising either vehicle safety or the impermeability of the road
surface (it is very important to keep water away from the concrete and steel
bridge structure to preserve its integrity).
This project will involve
complete removal of the asphalt and the 'protection board' material which is
below the asphalt. New protection board and asphalt will then be
applied. Camrose drive will have to be closed to traffic for the duration
of the project.
ISL Engineering of Edmonton,
have been selected to design and manage the project.
City Council approved Millar
Western Industries Ltd as the prime Contractor for the project.
Budget and Funding
|
Total Project Cost
|
$225,000.00
|
|
City of Camrose Contribution
|
$90,000.00
|
|
Provincial Transportation Grant
|
$135,000.00
|
Schedule
- Project Final Design - January to April 2001
- Project Tender - May 2001
- Project Award - May 28, 2001
- Construction Start - June 18, 2001
Phase One Construction - South Side of Bridge
- East Bound Lane - June 18 to July 4.
- Traffic was limited to the single North Lane with traffic signals
stopping and controlling traffic.
- Construction of this phase took longer than anticipated. The
project involved a lot of hand labour to remove the old membrane.
The contractor worked double shifts to get the road fully open prior to
the Rock Concert.
|

|

|
|
June 20, 2001. Crews removing existing Asphalt
surface from the bridge deck using a Roto-Milling machine. Test
holes shown in a grid pattern in the foreground were used to determine
asphalt thickness so that damage to the underlying waterproofing
membrane during asphalt removal is minimized. |
June 21, 2001. Hand removal of deteriorated
waterproofing membrane protection board and remaining asphalt. Any
Damage to the existing waterproofing membrane must be repaired prior to
installation of the new protection board and asphalt wearing surface. |
|

|

|
|
July 8, 2001. Sandblasting damaged membrane areas for new
membrane application. |
July 10, 2001. Applying prime coat to prepared concrete
surface for new membrane. |
|

|

|
|
July 10, 2001. Installing new hot rubberized asphaltic
membrane to prepared concrete surfaces and to existing membrane c/w new
protection board, 10 mm overall thickness. |
July 11, 2001. Placing first 40 mm lift of new ACP over
waterproofing membrane system. |
|

|

|
|
July 12, 2001. Placing second 40 mm lift of new ACP. |
July 12, 2001. Completed EBL re-opened to traffic. Temporary
"Davidson Markers" delineate centerline. |
Phase Two Construction - North Side of Bridge
- West Bound Lane
- Phase Two Construction started August 13, 2001 thereby avoiding the
Jamboree and Rock Concert Traffic
- During construction of Phase Two, the North Lane will be closed and two
way traffic will be allowed on the South Lane using the same traffic
signal control system as was used in phase one.
- The project is expected to be complete by September 7, 2001.
Removal of the asphalt was completed August 15, 2001.
Removal of the protection board was a slow
process involving a lot of hard manual labour. Because of the daytime
temperatures, crews worked two night shifts. This work was complete by August 27, 2001.
Once the old protection board was removed, the bridge deck was sand blasted
( two days), and a new waterproofing membrane was
then be installed followed by paving.
The project was completed in early September 2001.
For More Information Contact the Engineering Department at 672-4428.
|